NEW QUESTION 26
Which of the following are the two features of the Scrum Teams? (Choose two.)
- A. Can have multiple Product Owner's
- B. Cross-functional
- C. Rules of Etiquette
- D. Process Oriented
Answer: B,C
Explanation:
Explanation/Reference:
NEW QUESTION 27
Which three questions are answered by all Development Team members at the Daily Scrum? (Choose three)
- A. What impediments are in the way of my accomplishing my work?
- B. Why were you late?
- C. What work am I going to do today?
- D. What work did I do yesterday?
- E. How is the Sprint proceeding?
Answer: A,C,D
NEW QUESTION 28
What is the Scrum?
- A. It's not a Agile Framework
- B. Scrum is a complete process to develop software
- C. A framework within which people can address complex adaptive problems, while productively and creativelydelivering products of the highest possible value
- D. None of above
Answer: C
NEW QUESTION 29
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
- A. The Scrum Team
- B. The Product Owner
- C. The Project Manager
- D. The Development Team
Answer: D
NEW QUESTION 30
When many Scrum Teams are working on a project, what best describes the definition of "done"?
- A. Each Team uses its own but must make it clear to all other Teams
- B. All teams must use the same definition
- C. It depends
- D. Each Team defines and uses its own
Answer: B
NEW QUESTION 31
Which of the following is reflected in a Sprint Burn down Chart?
- A. Number of Tasks Remaining
- B. Work Hours Remaining
- C. Team Members Name
- D. Number of Product Backlog Items Completed
Answer: B
NEW QUESTION 32
The Product Backlog is maintained by:
- A. The Development Team
- B. The Product Owner and Scrum Master
- C. The Scrum Master
- D. The Product Owner
Answer: D
NEW QUESTION 33
Please select which statement is the most accurate:
- A. Agile Development and Scrum are synonyms for the same methodology
- B. Agile Development and Scrum are contrasting methodologies
- C. Scrum is an implementation of Agile Development
- D. Agile Development is an implementation of Scrum
Answer: C
NEW QUESTION 34
You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item.
How should the development team handle the remaining three tasks?
- A. The development team should keep the three tasks on the Sprint Backlog for the next Sprint and complete those tasks first
- B. The development team should place the two Product Backlog items back onto the Product Backlog
- C. The development team should work the extra 8 hours to complete their commitment to the Product Owner
- D. The development team should negotiate with the Product Owner on the definition of "done".
Answer: D
NEW QUESTION 35
Which objectives are covered as part of Sprint Planning?
- A. Understanding what functionality the Product Owner desires within the next Sprint and figuring out how to doit.
- B. Reviewing current functionality that binds the software solution
- C. Recalculating empirical velocity, adjusting team capacity accordingly, and projecting end dates
- D. Updating the scope of the release with all Sprints, end dates, and costs
Answer: A
NEW QUESTION 36
How many hours per day should a person on a Scrum team work?
- A. However many hours are needed to get the work done.
- B. A sustainable pace, usually from 7-8 hours per day.
- C. An "ideal day" measuring only when he or she is productive.
- D. 14 hours.
Answer: B
NEW QUESTION 37
What is the Release Burn down?
- A. The work remaining to be completed by the Product Owner
- B. A measure of the remaining Product Backlog across the time of a release plan
- C. What has been completed by the Scrum Team to date
- D. A graph indicating what has been completed by the Scrum Team
Answer: B
Explanation:
Explanation/Reference:
NEW QUESTION 38
Which of the following is a role in the Scrum framework?
- A. Development Team
- B. QA Tester
- C. Database Admin
- D. Senior Developer
Answer: A
NEW QUESTION 39
Which statement best describes what it means for an activity to be time-boxed?
- A. There is a recommended amount of time for the activity
- B. There is a maximum time limit for the activity
- C. The activity must take place on a particular date
- D. The activity must start at a particular time
Answer: B
NEW QUESTION 40
___________________is responsible for the Scrum process, facilitate the team and protect the team from outside noise.
- A. Product Owner
- B. Scrum Master
- C. Stakeholder
- D. Scrum Owner
Answer: B
NEW QUESTION 41
Which of the following questions is not relevant for regular Scrum Meeting?
- A. What impedes you from perfuming your work as effectively as possible?
- B. What will you do between now and next Daily Scrum meeting regarding this project?
- C. Would you be able to finish your work on time?
- D. What have you done since the last Daily Scrum regarding this project?
Answer: C
Explanation:
Explanation/Reference:
NEW QUESTION 42
You are the Scrum Master and the very first Sprint will complete in 5 days. You are creating a meeting invite for the Sprint Review to demo the items completed in the Sprint. Who should you invite as a required attendee to the Sprint Review?
1. Product Owner(s)
2. Development Team
3. Business Users
- A. 1 and 2 only
- B. The entire company
- C. 1 only
- D. 1, 2, and 3
Answer: A
Explanation:
Explanation
NEW QUESTION 43
The Scrum Framework encompasses rules or guidelines for architecture?
- A. False
- B. True
Answer: A
NEW QUESTION 44
Who is on the Scrum Team?
- A. Project Owner
- B. Scrum Master
- C. Development Team
- D. CEO
- E. Manager
- F. Project Manager
- G. Product Owner
Answer: B,C,G
NEW QUESTION 45
Which of these may a Development Team deliver at the end of a Sprint (choose 2)?
- A. An increment of software with minor known bugs in it
- B. A single document, if that is what the Product Owner asked for
- C. Failing unit tests, to identify acceptance tests for the next Sprint
- D. An increment of working software that is "done."
Answer: B,D
NEW QUESTION 46
During the sprint review the project is assessed against the ____________
- A. Sprint retrospective
- B. Sprint goal
- C. Sprint review
- D. Sprint Planning
Answer: B
NEW QUESTION 47
The Sprint planning meeting is comprised of how many sections?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: C
NEW QUESTION 48
True or False: Scrum is a collaborative effort involving developers and customers in an ongoing dialog?
- A. True
- B. False
Answer: A
NEW QUESTION 49
What is the maximum amount of time a sprint retrospective should take?
- A. 1 and half hour
- B. 1 hour
- C. 3 hours, for an 30 days Sprint
Answer: C
NEW QUESTION 50
......