[Nov 10, 2021] Prepare For The C-ACTIVATE13 Question Papers In Advance [Q71-Q89]

Share

[Nov 10, 2021] Prepare For The C-ACTIVATE13 Question Papers In Advance

C-ACTIVATE13 PDF Dumps Real 2021 Recently Updated Questions

NEW QUESTION 71
What is a difference between the SAP Activate methodology for a new implementation of SAP S/4HANA cloud edition and a new implementation of SAP S/4HANA on-premise?
Please choose the correct answer.
Response:

  • A. For the cloud edition, there is an additional Q-Gate for integration with on-premise systems
  • B. For the cloud edition, there is an additional work stream for integration with on-premise systems
  • C. For on-premise, there is an additional Q-Gate for system installation
  • D. For on-premise, there are additional deliverables for the system setup

Answer: D

 

NEW QUESTION 72
Your project is preparing for the Fit/Gap analysis workshops. If you use the Agile approach, what sequence of activities do you perform in the Explore Phase?
Please choose the correct answer.
Response:

  • A. a. Set reference value
    b. Prioritize initial backlog
    c. Conduct Delta Design workshops
    d. Conduct Solution Validation workshops
  • B. a. Conduct Solution Validation workshops
    b. Conduct Delta Design workshops
    c. Set reference value
    d. Prioritize initial backlog
  • C. a. Conduct Solution Validation workshops
    b. Set reference value
    c. Prioritize initial backlog
    d. Conduct Delta Design workshops
  • D. a. Set reference value
    b. Conduct Solution Validation workshops
    c. Prioritize initial backlog
    d. Conduct Delta Design workshops

Answer: D

 

NEW QUESTION 73
Which of the following is not correct about Fit/Gap Analysis?
There are 2 correct answers to this question.
Response:

  • A. Drive towards adopting customers processes.
  • B. Validate pre-activate and pre-assembled solution in the development system.
  • C. Minimize the needs for rework during realization.
  • D. Prioritize delta requirement and gaps.

Answer: A,B

 

NEW QUESTION 74
Which statements are part of the 5 Golden Rules for SAP S/4HANA Cloud, Single Tenant Edition?
There are 2 correct answers to this question.
Response:

  • A. Use SAP Solution Manager 7.2 with Focused Build.
  • B. Stick to the security standards of the customer organization.
  • C. Document deviations from Golden Rules for transparency and future use in upgrades.
  • D. Foster a cloud mindset and adherence to the Fit-to-Standard approach.

Answer: C,D

 

NEW QUESTION 75
Why is there NO Sandbox system in the "New Implementation of SAP S/4HANA Cloud, Single Tenant Edition" transition path?
Please choose the correct answer.
Response:

  • A. Because the customer may use the SAP Model Company
  • B. Because the Fit-to-Standard workshop is conducted using the Q-system
  • C. Because SAP S/4HANA Cloud, Single Tenant Edition, contains predefined business processes which should NOT be changed
  • D. Because the project team uses the DEV system to confirm solution fit and define delta requirements

Answer: A

 

NEW QUESTION 76
What is the difference between the "System Conversion and the "New Implementation of SAP S/4HANA" transition paths?
There are 2 correct answers to this question.
Response:

  • A. In the Realize phase, custom code is adjusted rather than developed for System Conversion.
  • B. There are different upgrade cycles.
  • C. SSCUls are used in System Conversion for configuring SAP S/4HANA through the Manage Your Solution app.
  • D. In the Realize phase, data is converted and NOT migrated for System Conversion.

Answer: A,D

 

NEW QUESTION 77
Where can you find Data Migration templates?
Please choose the correct answer.
Response:

  • A. SAP Cloud Appliance Library
  • B. SAP S/4HANA Migration Cockpit
  • C. SAP Roadmap Viewer
  • D. SAP Best Practices Explorer

Answer: B

 

NEW QUESTION 78
In SAP Activate, what replaces the detailed Blueprint from ASAP?
Please choose the correct answer.
Response:

  • A. Custom Extension management
  • B. Business Process Mapping
  • C. Value Determination
  • D. Fit/Gap Workshops

Answer: D

 

NEW QUESTION 79
What is the purpose of the Solution Builder tool in the SAP Activate Guided Configuration?
Please choose the correct answer.
Response:

  • A. To personalize activated, ready-to run business processes
  • B. To create customer-specific scope items
  • C. To create delta building blocks for complementary content
  • D. To activate the Best Practices content

Answer: D

 

NEW QUESTION 80
What is the objective of a sprint retrospective meeting?
Please choose the correct answer.
Response:

  • A. Review and prioritize the backlog
  • B. Define the stakeholder management approach
  • C. Improve the SCRUM process
  • D. Provide formal feedback to the project manager

Answer: C

 

NEW QUESTION 81
Which of the following tasks are part of the Production support after the Go Live key deliverable?
There are 2 correct answers to this question.
Response:

  • A. Perform a Technical systems test
  • B. Provide further training to customer end users
  • C. Resolve issues identified during the Hyper Care period
  • D. Set up the Operations Control Center

Answer: B,C

 

NEW QUESTION 82
How would you describe the Explore phase in the "New Implementation of SAP S/4HANA Cloud" transition path?
Please choose the correct answer.
Response:

  • A. Solution Validation and Delta Design
  • B. Simplification and Custom Code Impact Analysis
  • C. Fit-to-standard
  • D. Setup and Enablement

Answer: C

 

NEW QUESTION 83
Which Value Chains does SAP Solution Manager 7.2 deliver?
There are 3 correct answers to this question.
Response:

  • A. Detect-to-Correct
  • B. Cash-to-Order
  • C. Requirements-to-Deploy
  • D. Request-to-Fulfill
  • E. Hire-to-Retire

Answer: A,C,D

 

NEW QUESTION 84
What is the minimum number of quality gates mandated by the SAP Activate methodology?
Please choose the correct answer.
Response:

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: D

 

NEW QUESTION 85
Which key activities does the Guided Configuration support you with?
There are 3 correct answers to this question.
Response:

  • A. Train new users
  • B. Test configured processes
  • C. Create test data
  • D. View solution scope
  • E. Manage roles of configuration users

Answer: A,B,E

 

NEW QUESTION 86
Which accelerators support the Fit-to-standard workshop in the Explore phase?
There are 2 correct answers to this question.
Response:

  • A. Business-Driven Configuration Questionnaire
  • B. Quality Gate Checklist
  • C. Backlog template
  • D. Test Strategy

Answer: A,C

 

NEW QUESTION 87
Which of the following activities are part of the Deploy Phase of a Landscape Transformation journey to SAP S/4HANA On-Premise Edition?
There are 2 correct answers to this question.
Response:

  • A. Solution Activation
  • B. Optimize software Change Control Management
  • C. Training delivery
  • D. Access organizational and production readiness

Answer: C,D

 

NEW QUESTION 88
What are the three elements of SAP Activate?
There are 3 correct answers to this question.
Response:

  • A. Focused Build
  • B. SAP Solution Manager
  • C. Tools
  • D. Content
  • E. Methodology

Answer: C,D,E

 

NEW QUESTION 89
......


SAP Activate Project Manager Certification Exam Topics:

Topic AreasTopic Details, Courses, BooksWeighting
SAP Activate OverviewDefine factors influencing SAP Activate, its purpose and place among other frameworks.

ACT100 (SAP S/4HANA 1809)

> 12%
Transition Path "Selective Data Transition"Describe concepts, landscape overview and specifics in Workstreams related to “Selective Data Transition” Transition Path.

ACT100 (SAP S/4HANA 1809)

< 8%
Transition Path "New Implementation SAP S/4HANA Cloud"Describe concepts, landscape overview, and specifics in Workstreams related to implementing SAP S/4HANA Cloud.

ACT100 (SAP S/4HANA 1809)

8% - 12%
Workstreams OverviewDescribe concepts, artefact flows, accelerators, tools and roles for each Workstream within SAP Activate Methodology.

ACT100 (SAP S/4HANA 1809)

> 12%
Transition Path "System Conversion"Describe concepts, landscape overview and specifics in Workstreams related to “System Conversion” Transition Path.

ACT100 (SAP S/4HANA 1809)

< 8%
Transition Path "New Implementation SAP S/4HANA On Premise"Describe concepts, landscape overview and specifics in Workstreams related to implementing SAP S/4HANA On Premise.

ACT100 (SAP S/4HANA 1809)

< 8%
Agile Project PlanningDescribe the agile project roles and responsibilities and the preparation of the project including the planning, estimation, user story mapping and construction of backlog.

ACT100 (SAP S/4HANA 1809)
ACT200 (SEE COURSE DETAIL)

8% - 12%
Agile Project DeliveryDescribe how the project team prepares release and sprint plans, and the structure and key activities in each sprint. Discuss key techniques used in agile projects.

ACT100 (SAP S/4HANA 1809)
ACT200 (SEE COURSE DETAIL)

> 12%
SAP Activate ElementsProvide an overview of content, tools and methodology elements of SAP Activate Solution Implementation Framework.

ACT100 (SAP S/4HANA 1809)

> 12%

 

C-ACTIVATE13 Dumps and Practice Test (169 Exam Questions): https://www.realexamfree.com/C-ACTIVATE13-real-exam-dumps.html

Released SAP C-ACTIVATE13 Updated Questions PDF: https://drive.google.com/open?id=1W3zo1iBnCCytLQwCZXNFnuQg2Qdz_P-K