2022 Realistic CPIM-BSCM Dumps Latest APICS Practice Tests Dumps [Q68-Q92]

Share

2022 Realistic CPIM-BSCM Dumps Latest APICS Practice Tests Dumps

CPIM-BSCM Dumps PDF - CPIM-BSCM Real Exam Questions Answers


What is the cost of APICS CPIM - BSCM

The cost of APICS CPIM - BSCM is $250.

  • Passing Score: 63%
  • Number of Questions: 80
  • Format: Multiple choices, multiple answers
  • Length of Examination: 180 minutes

Difficulty in Attempting APICS CPIM - BSCM

  • CPIM gives experiences into how the different pieces cooperate and what apparatuses, approaches, innovations and estimations uphold and empower accomplishment of production network destinations
  • Supply affix the board experts need to comprehend the communications and between conditions across the capacities, and the regularly clashing pressing factors and objectives of the different members
  • The store network is about participation and coordinated effort
  • A CPIM assignment shows a grip of that information and reports the person’s competence─for the advantage of both the individual and the association
  • CPIM can give devices to assist you with improving activities, increment consumer loyalty and friends benefit

We offer:

  • Updated design conveys a similar CPIM information and abilities in an engaged program to meet the preparation needs of the present occupied inventory network experts
  • The new CPIM Learning System is a demonstrated APICS confirmation readiness technique that consolidates perusing materials with online practice tests and apparatuses
  • Streamlined confirmation experience gets you guaranteed quicker
  • Simplified and centered investigation materials consolidates the time and exertion it takes to plan for the CPIM test

Certificate questions has assembled the vault for the biggest arrangement of training addresses which are accessible as APICS CPIM-BSCM practice exam and APICS CPIM-BSCM practice tests to set you up in the most ideal manner for the test.

NEW QUESTION 68
Which of the following forecast inputs is considered to be intrinsic data?

  • A. Historical sales
  • B. Demographic
  • C. Market survey
  • D. Econometric

Answer: A

 

NEW QUESTION 69
Consignment stock is typically owned by:

  • A. a joint trust set up for this purpose.
  • B. a supplier until consumed.
  • C. the carrier who transports the stock.
  • D. the company who will consume the stock.

Answer: B

 

NEW QUESTION 70
Effective inventory management should lead to which of the following?

  • A. Elimination of inventory cycle counting
  • B. Lower cost of capital
  • C. Higher inventory turns
  • D. Higher product quality

Answer: C

 

NEW QUESTION 71
Material requirements planning provides recommendations for which of the following processes?

  • A. Routing and lead times
  • B. Shop orders and capacity
  • C. Capacity and purchase orders
  • D. Purchase orders and shop orders

Answer: D

 

NEW QUESTION 72
Which of the following terms represents a complete supply chain dedicated to the flow of products and
materials for the purpose of returns, repair, remanufacture, or recycling?

  • A. Responsible landfill
  • B. Global distribution
  • C. Reverse logistics
  • D. Remanufacturing resource planning

Answer: C

 

NEW QUESTION 73
The theory of constraints is most effective when:

  • A. the constraint cannot be identified easily.
  • B. the constraint cannot be managed easily.
  • C. demand environments are unstable.
  • D. demand environments are stable.

Answer: D

 

NEW QUESTION 74
Which of the following processes is concerned with the transfer or delivery of goods or services?

  • A. Transaction channel
  • B. Value chain
  • C. Distribution channel
  • D. Supply chain

Answer: C

 

NEW QUESTION 75
Which of the following issues would be of greatest concern for a company choosing to reduce its finished
goods inventory?

  • A. Long production changeover time
  • B. Product quality requirements
  • C. Customer service expectations
  • D. Product shelf life constraints

Answer: C

 

NEW QUESTION 76
The complete supply chain dedicated to the flow of products for returns, repair and remanufacturing is:

  • A. reverse logistics.
  • B. reverse auction.
  • C. reverse flow scheduling.
  • D. reverse engineering.

Answer: A

 

NEW QUESTION 77
A firm offers products configured from a large number of stocked options. Which of the following
production environments is the firm most likely to use?

  • A. Make-to-order
  • B. Engineer-to-order
  • C. Make-to-stock
  • D. Assemble-to-order

Answer: D

 

NEW QUESTION 78
Which of the following plans is translated into synchronized functional plans through the sales and
operations planning process?

  • A. Financial
  • B. Strategic
  • C. Business
  • D. Marketing

Answer: C

 

NEW QUESTION 79
Which of the following information is the key output of rough-cut capacity planning?

  • A. Inventory objectives by product line
  • B. Capacity requirements plan
  • C. Line balancing
  • D. Critical resource availability

Answer: D

 

NEW QUESTION 80
Inventory turns is an appropriate performance measure for which of the following functions?

  • A. Total quality management
  • B. Material control
  • C. Activity-based costing control
  • D. Flexible manufacturing

Answer: B

 

NEW QUESTION 81
Which of the following considerations should be included in product design?

  • A. Environmental sensitivity
  • B. Manufacturing strategy
  • C. Target markets
  • D. Product pricing

Answer: A

 

NEW QUESTION 82
An order winner is a competitive characteristic that:

  • A. differentiates among potential customers.
  • B. a company must exhibit to be considered a potential supplier.
  • C. a company must exhibit to gain new sales.
  • D. is universal between customers and markets.

Answer: C

 

NEW QUESTION 83
A manufacturer's market is highly dependent upon customers selecting standard options at the time of
placing an order. Which of the following manufacturing strategies is best suited to compete in this market?

  • A. Make-to-order
  • B. Engineer-to-order
  • C. Make-to-stock
  • D. Assemble-to-order

Answer: D

 

NEW QUESTION 84
Which of the following considerations is an advantage of sourcing from multiple suppliers?

  • A. Shorter lead times
  • B. Better quality
  • C. Competition
  • D. Opportunity for partnering

Answer: C

 

NEW QUESTION 85
If the quantity ordered equals the quantity required in a time bucket, which of the following lot-sizing rules
has been used?

  • A. Fixed order quantity
  • B. Order "N" periods supply
  • C. Economic order quantity (EOQ)
  • D. Lot-for-lot

Answer: D

 

NEW QUESTION 86
Which of the following measures should a company focus on to reduce variation in the product?

  • A. Median
  • B. Mean
  • C. Standard deviation
  • D. Mode

Answer: C

 

NEW QUESTION 87
Which of the following capacity management techniques is used to support the production plan?

  • A. Resource planning
  • B. Input/output control
  • C. Capacity requirements planning
  • D. Rough-cut capacity planning

Answer: A

 

NEW QUESTION 88
Which of the following manufacturing systems involves the creation of one unit or a small number of
units?

  • A. Flow manufacturing
  • B. Intermittent manufacturing
  • C. Continuous manufacturing
  • D. Project manufacturing

Answer: D

 

NEW QUESTION 89
Which of the following actions is an example of a company expanding its customer service offering?

  • A. Implementing statistical process control (SPC)
  • B. Increasing work-in-process (WIP) inventory
  • C. Decreasing manufacturing lot sizes
  • D. Adding a distribution center

Answer: D

 

NEW QUESTION 90
Part A is made from two Y's and one X.
An order is received for 50 A's and there are 30 A's in stock.
What is the net requirement for X?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: B

 

NEW QUESTION 91
Which of the following systems typically involves design while manufacturing is occurring?

  • A. Intermittent
  • B. Flow
  • C. Engineer
  • D. Project

Answer: D

 

NEW QUESTION 92
......

CPIM-BSCM Premium Exam Engine pdf Download: https://www.realexamfree.com/CPIM-BSCM-real-exam-dumps.html